Professional tools for serious builders  Start Here or
Renewables Guide

Planning and Regulations for Renewables

Which consents and approvals apply to each technology, and who is responsible for getting them.

Home›Renewables Guide›Planning and Regulations
Figures and rules last verified October 2026. They change, so check the sources linked on this page.
Quick answer

Most domestic solar PV, air source heat pumps and EV chargers in England can be installed under permitted development, but each has conditions, and listed buildings, conservation areas and flats are treated differently. Separate from planning, the electrical work, grid connection and Building Regulations may still apply.

Rules differ in Scotland, Wales and Northern Ireland and have changed recently, so always check the current position with your council before you commit.

Four separate things to check

At a glance by technology (England)

TechnologyPlanningOther approvals
Solar PVUsually permitted development, with conditions. Rules amended from 27 August 2026G98 or G99, electrical safety certificate, roof loading check
Air source heat pumpUsually permitted development, with noise and other conditions. Rules changed 29 May 2025MCS for the grant, electrical work, ventilation and heating commissioning
BatteryUsually no separate planning if installed inside or alongside existing propertyG98 or G99, fire and siting safety
EV chargerOften permitted development, with conditions on size and positionElectrical certificate, supply capacity, Part S for new builds
Wind turbineUsually needs planning permissionG99, MCS for export payments, possible environmental checks
Solar thermal and biomassSolar thermal often permitted development. Biomass flues and stores have conditionsSmoke control rules, flue and combustion air requirements

This table is a guide only. Always confirm the current rules for your property and location.

Planning permission and permitted development

Permitted development lets you carry out some work without a full planning application. It does not apply to every property. It is limited or withdrawn for listed buildings, may be restricted in conservation areas, National Parks and similar designated land, and may have been removed by an Article 4 direction in your area. Flats and maisonettes generally need separate treatment because the roof and external walls are not yours alone.

Use our permitted development checker and read how to get planning permission if you need an application. A lawful development certificate can give written confirmation that your project is permitted.

Building Regulations

Renewables work often touches several parts of the Building Regulations, including structure (roof loading), electrical safety (Part P), fire safety, ventilation, and the energy performance of the dwelling. Installers registered with a competent person scheme can self-certify much of this and issue a certificate. If they are not registered, you may need to involve building control, which adds time and cost. For new builds, requirements such as the one for EV charge points apply as part of the wider design. Our building regulations checker helps you see what applies.

Electrical safety and grid connection

Certification, grants and export payments

MCS certification is not a legal requirement, but you generally need it for the Boiler Upgrade Scheme and the Smart Export Guarantee. See the MCS certification guide and the Boiler Upgrade Scheme page.

The other UK nations

Scotland, Wales and Northern Ireland have their own planning and building standards systems, grant schemes and sometimes different thresholds. Do not assume that an English rule applies. Check with the relevant local authority and national planning guidance.

Practical checklist

  1. Check whether your property is listed, in a conservation area or subject to an Article 4 direction.
  2. Run the permitted development checker, then confirm with your council if there is any doubt.
  3. Ask your installer which competent person scheme they use and who handles grid notification.
  4. Agree who will provide the planning evidence, certificates and MCS paperwork before work starts.
  5. Keep every certificate in one folder for the sale of the property.

Sources and further reading

External links open in a new tab. Last checked October 2026.

Frequently asked questions

Do I need planning permission for solar panels or a heat pump?

Often not in England, because both can be permitted development, but conditions apply and rules differ for listed buildings, conservation areas, flats and the other UK nations. Check before you commit.

Do renewables need Building Regulations approval?

Often parts of the work do, such as electrical safety, structure and ventilation. A competent person scheme installer can usually self-certify, otherwise you may need building control.

Do I need to tell my electricity network operator?

Yes for generation and batteries. Small systems are notified under G98 within 28 days of commissioning, and larger ones need approval under G99 first.

What is permitted development?

It is a national grant of planning permission for certain works, subject to conditions. It is limited for listed buildings and may be restricted in conservation areas or by an Article 4 direction.

Are the rules the same across the UK?

No. Scotland, Wales and Northern Ireland have their own planning and building standards, so check the rules that apply where the property is.

Next guide Choosing an Installer MCS checks, comparing quotes, deposits and warning signs. Read the guide

Related guides and tools

This page is general guidance for information only. Costs, grants, tariffs and planning rules change, and individual properties differ. Costs are indicative ranges drawn from industry and government sources, not quotes. Always get written quotes from MCS-certified installers and confirm current rules with your local planning authority, Ofgem and gov.uk.