50+ Specialist Calculators
Instant Results - No Sign-Up
Free to Use
Professional tools for serious builders
Free Word Download

Variation Order Template

A formal written instruction for any change to the agreed scope of work - covering cost, programme impact and dual sign-off. The single most effective way to avoid end-of-project disputes over extras.

HomeProject Management TemplatesVariation Order

What is a variation order?

A variation order (VO) - sometimes called a change order or instruction - is a formal written document that records an agreed change to the original scope of work. It records what has been added, omitted or changed, the agreed cost and any extension of time to the programme. Both parties sign it before the extra work begins.

A signed variation order forms a legally binding amendment to the contract. Without one, recovering payment for extras becomes extremely difficult - even if both parties have verbally agreed the change.

Never start extra work on a verbal agreement alone. Issue the variation order, get it signed, then proceed. A client who is happy to agree verbally on a Tuesday morning may have no recollection of the conversation by the time the final account lands.

What's included in the template

Extension of time - when to claim it

If the variation adds work that extends the programme, you must also agree and record an extension of time (EOT). If you do not, the contract completion date remains unchanged and the contractor risks liquidated damages if the project overruns - even if the client's own instruction caused the delay.

The EOT should be agreed at the same time as the cost, not after the fact. Be realistic about the programme impact - clients generally accept a reasonable EOT claim more readily before the work starts than when they are already frustrated by delays.

Contractor and client signing a variation order document on a construction site

Frequently asked questions

What is a variation order in construction?
A variation order is a formal written instruction to change the scope of work agreed in the original contract. It records what has been added, omitted or changed, the agreed cost and any programme extension. Signed by both parties before work begins, it forms a legally binding amendment to the contract.
What happens if I do extra work without a signed VO?
Without a signed variation order, recovering payment for extra work becomes very difficult. A client can argue the work was included in the original scope, that it was inferior to what was agreed, or that they never authorised it. The contractor then has to prove the variation on balance of probabilities - a costly and uncertain process.
Can I use this template on a JCT contract?
JCT contracts have their own variation mechanisms (typically a Variation Instruction issued by the Contract Administrator). This template is designed for informal or letter-form contracts where there is no formal CA. Always check your specific contract conditions. For formal JCT projects, variations should be processed through the contract's own procedures.
What numbering system should I use for VOs?
Use a simple sequential number: VO-001, VO-002 etc. Keep a separate VO log (you can use a tab in our site diary spreadsheet) showing each VO number, date, brief description, value and current status. This makes it easy to track the cumulative variation account throughout the project.